抚顺西露天矿东区开采14段站移设工程

14 stage station shift project in the eastern area of Fushun West Open-pit Mine

尹有德1

作者信息

  • 1. 抚顺矿业集团有限责任公司 东露天矿,辽宁 抚顺 113003
  • 折叠

摘要

Abstract

This article introduces the operation process of 14 stage station north shift project in the eastern area of Fushun West Open-pit mine. From the economy and technology aspect, the author analyzes and discusses 14 stage station north shift project and presents the suitable mining scheme.

关键词

露天矿/开采/移设工程/剥离

Key words

East open-pit Mine/West open-pit mine/eastern area mining/shift project/stripping