铁道标准设计2017,Vol.61Issue(3):91-96,6.DOI:10.13238/j.issn.1004-2954.2017.03.020
昆山南站站房改造工程对既有高铁桥梁安全影响分析
Safety Analysis of the Impact of Kushan South Railway Station Reconstruction on Existing High-speed Railway Bridge
杜伟 1段鈜1
作者信息
- 1. 中铁第四勘察设计院集团有限公司,武汉 430063
- 折叠
摘要
Abstract
In this paper, the ABAQUS finite element program is used to analyze the influences of the Kushan south railway station reconstruction on the pier, foundation bearing capacity and deformation of the adjacent high speed railway bridge. The results of numerical simulation analysis show that (1) after the completion of the additional Kushan south railway station structures, both the bearing capacity and local stress of the bridge pier of HSR satisfy the requirement of design and standard; ( 2 ) the friction, shear force and bending moment of HSR bridge pile foundation have no obvious change during and after the construction of the building pile foundation, but the axial force increases obviously after the upper load is in place; the bridge pier tends to incline to the new construction areas, but the change of horizontal displacement and vertical settlement of pier are less than 1 mm of the control limit;(3) the cement mixing pile is able to reinforce the foundation, but it's necessary to keep a safe distance between the mixing pile and the pier foundation due to the adverse effect caused by the construction on the bridge foundation.关键词
高铁桥梁/数值模拟/ABAQUS软件/水泥搅拌桩/安全影响Key words
High-speed railway bridge/Numerical simulation/ABAQUS software/Cement mixing pile/Safety impact分类
交通工程引用本文复制引用