广东电力2017,Vol.30Issue(5):63-68,6.DOI:10.3969/gddl/gddl2017/1705/170512.htm
计及检修计划影响的水火发电系统可靠性评估
Reliability Evaluation for Hydro-thermal Generation System Considering Impact of Maintenance Schedules
黄柳强 1刘俊宏 2吴茵 1杨小卫 1郭瑞鹏2
作者信息
- 1. 广西电网有限责任公司电力调度控制中心,广西 南宁 530023
- 2. 浙江大学 电气工程学院,浙江 杭州 310027
- 折叠
摘要
Abstract
Stochastic production simulation is an important method for reliability evaluation for the hydro-thermal generation system. On the premise of considering impact of maintenance schedule for hydro-thermal generator on reliability evaluation for the generation system, this paper presents an interval-coordinated stochastic production simulation method for dividing the study period into intervals according to maintenance state of the generator. By coordinating different time periods, this method can determine working capacity of the hydro-thermal generator and then make stochastic production simulation on the generator in each time period independently. Since simulation order of the full-capacity generator has no influence on the residual load duration curve and reliability index, this paper preferentially simulates the thermal generator and then the hydro generator, which can avoid searching economy load position and greatly improve computation speed of reliability evaluation. Testing results of one small system and an actual provincial power grid verify validity and computation speed of the proposed method.关键词
水火发电系统/检修计划/可靠性评估/随机生产模拟/持续负荷曲线Key words
hydro-thermal generation system/maintenance schedule/reliability evaluation/stochastic production simulation/load duration curve分类
信息技术与安全科学引用本文复制引用
黄柳强,刘俊宏,吴茵,杨小卫,郭瑞鹏..计及检修计划影响的水火发电系统可靠性评估[J].广东电力,2017,30(5):63-68,6.