广东电力2017,Vol.30Issue(6):17-21,5.DOI:10.3969/j.issn.1007-290X.2017.06.004
三汽包余热锅炉调峰机组汽水品质控制方法
Quality Control for Steam Water in Three-drum Heat Recovery Boiler of Peaking Unit
朱樱雅 1李欣2
作者信息
- 1. 深圳前湾燃机电厂,广东 深圳 518054
- 2. 广东电网有限责任公司电力科学研究院,广东 广州 510080
- 折叠
摘要
Abstract
In order to meet requirements for rapid startup of the peaking unit and steam combination of boilers, this paper studies change law of steam water quality. It firstly summarizes characteristic of the three-drum heat recovery boiler and operation mode speciality of the peaking unit as well as discusses existing problems. Then it proposes control optimization method for condensation water and steam and sums up control measures and method for steam water quality. By strictly controlling exception handling for steam water, conditions for rapid startup and steam combination are established than can enable steam water quality of the unit quickly meet the national standard.关键词
三汽包余热锅炉/调峰机组/汽水品质/结盐与腐蚀Key words
three-drum heat recovery boiler/peaking unit/steam water quality/salt formation and corrosion分类
能源科技引用本文复制引用
朱樱雅,李欣..三汽包余热锅炉调峰机组汽水品质控制方法[J].广东电力,2017,30(6):17-21,5.