| 注册
首页|期刊导航|工程地质学报|云南成品油管道安宁高填方边坡变形规律研究

云南成品油管道安宁高填方边坡变形规律研究

高盛翔 葛华 蒋斌松 吴圣林 史继彪 吴泽辉

工程地质学报2017,Vol.25Issue(3):892-900,9.
工程地质学报2017,Vol.25Issue(3):892-900,9.DOI:10.13544/j.cnki.jeg.2017.03.039

云南成品油管道安宁高填方边坡变形规律研究

STUDY ON THE DEFORMATION LAW OF THE ANNING HIGH-FILL SLOPE IN YUNNAN REFINED OIL PIPELINE

高盛翔 1葛华 2蒋斌松 3吴圣林 1史继彪 3吴泽辉1

作者信息

  • 1. 徐州中国矿大岩土工程新技术发展有限公司 徐州 221008
  • 2. 中国石油天然气股份有限公司西南管道分公司 成都610041
  • 3. 中国矿业大学 徐州221008
  • 折叠

摘要

Abstract

With the rapid development of the infrastructure construction in southwestern mountainous areas in China.High-fill foundations of the Airport,Highways,Railways and other construction projects increase day by day.During the construction period,the large deformation of the fill area and long-term slow deformation of the post-construction stage directly affect the normal use of the construction site.Especially the fill works with the free faces of slope,slope and horizontal deformation of the rilled soil are related to the overall stability of slope.This paper takes a high-fill slope in Anning city in Yunnan province as a case.The site survey and the monitoring data during the filling process was used in the deformation analysis.The numerical simulation software was used to study the deformation characteristics of the fill slope.The results show that the total deformation of the slope is dominated by subsidence,and the maximum occurs in the interior of the slope.Most of the deformation occurs during the construction.The settlement after construction is very small.The maximum vertical displacement of the slope occurs at the interface between the filling body and the original foundation soil.The contour of settlement is elliptical.The maximum of horizontal displacement of the slope occurs in the original soil.Horizontal displacement contour map is overall strip-like.It extends from the bottom to the earth of the slope.The horizontal displacement that changes greatly is consistent with the position of the actual surface crack.The research results have certain reference value and guiding significance to the construction process of the fill work with free face,the prediction and control of the deformation after construction and the study on crack disease on the upper part of slope.

关键词

高填方边坡/坡体变形/工后变形/坡体裂缝/数值模拟

Key words

High fill slope/Slope deformation/Post-construction deformation/Slope crack/Numerical simulation

分类

天文与地球科学

引用本文复制引用

高盛翔,葛华,蒋斌松,吴圣林,史继彪,吴泽辉..云南成品油管道安宁高填方边坡变形规律研究[J].工程地质学报,2017,25(3):892-900,9.

工程地质学报

OA北大核心CSCDCSTPCD