| 注册
首页|期刊导航|水力发电学报|基于熵权-D数模型的RCC坝施工方案优选研究

基于熵权-D数模型的RCC坝施工方案优选研究

王乾伟 钟登华 鄢玉玲 时梦楠 任炳昱

水力发电学报2017,Vol.36Issue(7):104-112,9.
水力发电学报2017,Vol.36Issue(7):104-112,9.DOI:10.11660/slfdxb.20170711

基于熵权-D数模型的RCC坝施工方案优选研究

Optimization of RCC dam construction schemes using an entropy-D model

王乾伟 1钟登华 1鄢玉玲 1时梦楠 1任炳昱1

作者信息

  • 1. 天津大学 水利工程仿真与安全国家重点实验室,天津 300072
  • 折叠

摘要

Abstract

Optimization of RCC dam construction schemes is a typical multi-attribute decision-making process that requires a comprehensive consideration of several factors such as construction period,utilization rate of machines,and investment scale.Most previous studies neglected the influence of differences in the experts' knowledge and the fuzziness in the experts' judgment on construction scheme decision and assumed the index weights subjectively in optimization of the schemes without a clear mathematical basis.This paper describes an optimization method of RCC dam construction schemes using an entropy-D model that,based on the D-number theory,does not need the completeness of decision-making information.First,the Pearson correlation test method is used to analyze the correlation between evaluation indexes obtained from simulations of four schemes.Then,index weights are determined using an entropyweighted method and the D-number theory is applied to calculate the D-numbers of each scheme in different identification frames.Finally,combination rules of the D-numbers are determined and recursive combination is carried out according to the trust degrees of different experts and the weights of different indexes.And integration of these fusion results gives a comprehensive evaluation index of the schemes and hence an optimal scheme can be selected.Engineering applications show that this method can achieve an effective scheme optimization for RCC dam construction with incomplete decision information.

关键词

碾压混凝土坝/施工方案优选/D数理论/熵权法/综合评价指标

Key words

RCC dam/construction scheme optimization/D-number theory/entropy-weighted method/comprehensive evaluation index

分类

建筑与水利

引用本文复制引用

王乾伟,钟登华,鄢玉玲,时梦楠,任炳昱..基于熵权-D数模型的RCC坝施工方案优选研究[J].水力发电学报,2017,36(7):104-112,9.

基金项目

国家自然科学基金(51621092 ()

51439005) ()

国家重点基础研究发展计划(973计划)(2013CB035904) (973计划)

水力发电学报

OA北大核心CSCDCSTPCD

1003-1243

访问量0
|
下载量0
段落导航相关论文