摘要

Abstract

The dynamics process of construction dewatering of underground engineering was taken into account in this article. The method for calculating the water yield and dewatering time from the initial groundwater level to the target water level was established. Then, the design optimization of well group dewatering was provided with the consideration of water yield and dewatering time in dynamic dewatering process. Finally, the method for the calculation of water yield and dewatering time when dewatering regions change was derived. The reliability of this method was verified in on-site engineering applications.

关键词

工程降水/动态过程/排水量/排水时间/优化设计/动态控制

Key words

construction dewatering/dynamic process/water yield/dewatering time/optimal design/dynamic control

分类

交通工程

引用本文复制引用

施成华,蒋劲,雷明锋,彭立敏..考虑降水动态过程的地下工程施工降水优化设计[J].铁道科学与工程学报,2017,14(8):1597-1605,9.

基金项目

国家自然科学基金资助项目(51278494,U1361204) (51278494,U1361204)