Abstract
To solve failures in the slewing mechanism of MZ125/75 shipbuilding tower crane,the crane's electronic control system before transformation is analyzed,and a technical transformation plan is designed.Comparison of the electronic control system and operating status before and after the transformation shows that the transformed slewing mechanism is more stable,secure and accurate.关键词
造船塔式起重机/回转机构/电控系统/电气改造Key words
shipbuilding tower crane/slewing mechanism/electronic control system/electrical transformation分类
机械制造引用本文复制引用
丁冲,贾磊,郭晓光,钱红飙,焦博,魏兴..造船塔式起重机回转机构电气改造[J].起重运输机械,2017,(7):95-98,4.