地质力学学报2017,Vol.23Issue(3):498-506,9.
天津滨海新区地热资源循环利用研究——馆陶组热储回灌技术研究与示范
A STUDY ON THE RECYCLING UTILIZATION OF GEOTHERMAL RESOURCES IN BINHAI NEW AREA, TIANJIN——STUDY AND DEMONSTRATION OF THERMAL STORAGE AND REINJECTION TECHNOLOGY OF GUANTAO RESERVOIR
摘要
Abstract
Sustainable reinjection is the basis of geothermal resource recycling.The reason of reinjection decrease is summarized through the analysis of reservoir sensitivity,blocking factors,well completion structure and ground installation,in which it is believed that physical blocking is the main cause of reinjection blocking.The well completion structure is the key to keep sustainable reinjection,while standard ground equipment can help avoiding blocking caused by physical and chemical reasons.In this article,successful well completion construction and standard ground installation are applied to the demonstration project construction of geothermal resources recycling of thermal storage and reinjection of Guantao Reservoir,and the reinjection rate is 100 ~ 123 m3/h,which is a breakthrough of thermal storage and reinjection of Guantao Reservoir and guarantees the recycling of geothermal resources of Guantao Reservoir in Binhai New Area,Tianjin.关键词
天津/滨海新区/馆陶组热储/回灌研究/工程示范Key words
Tianjin/Binhai New Area/Guantao Reservoir/reinjection research/demonstration project分类
天文与地球科学引用本文复制引用
阮传侠,冯树友,沈健,林黎,江国胜..天津滨海新区地热资源循环利用研究——馆陶组热储回灌技术研究与示范[J].地质力学学报,2017,23(3):498-506,9.基金项目
矿产资源补偿费项目(国土房任[2009]27号) (国土房任[2009]27号)
国家自然科学基金青年科学基金项目(41502256) (41502256)