| 注册
首页|期刊导航|铁道标准设计|富水半成岩砂岩地层地铁车站深基坑变形监测与数值模拟分析

富水半成岩砂岩地层地铁车站深基坑变形监测与数值模拟分析

向亮

铁道标准设计2017,Vol.61Issue(11):121-127,7.
铁道标准设计2017,Vol.61Issue(11):121-127,7.DOI:10.13238/j.issn.1004-2954.2017.11.025

富水半成岩砂岩地层地铁车站深基坑变形监测与数值模拟分析

Monitoring and Numerical simulation of a Deep Foundation pit of a Metro Transfer Station in Water-rich Sandstone Strata

向亮1

作者信息

  • 1. 中铁第一勘察设计院集团有限公司,西安710043
  • 折叠

摘要

Abstract

Based on the excavation project of a metro transfer station in Lanzhou,the deformation law of deep foundation pit engineering in special bad geological conditions (red sandstone layer) is studied based on the analysis of the displacement of fender piles and axial force of the steel supports,and by means of the simulation of the excavation process of deep foundation pit and the comparison of the results of numerical simulation with those of the measurements.The monitoring and numerical simulation results showe that the deformation of the pile presents the shape of a " bow",most deformation of the pile appears in the surface of excavation;under normal construction,the surface settlement turns to be in a groove shape,and the deformation of the pile shows a triangle in shape in case fender piles are subject to water leak and sand leak;the steel strut axial pressure jumps up to the maximum after the next strut is put in place;where secant pile is used in deep foundation pit engineering as a retaining and sealing structure,the verticality of must be maintained to ensure pile quality;the calculation results are basically agree with the measurements and the numerical analysis provides the basis for the design and construction of foundation pit.

关键词

地铁车站/红砂岩/深基坑/变形/支撑轴力/地表沉降/监测/数值模拟

Key words

Metro station/Red sandstone/Deep foundation pit/Deformation/Strut force/Surface settlement/Monitoring/Numerical simulation

分类

交通工程

引用本文复制引用

向亮..富水半成岩砂岩地层地铁车站深基坑变形监测与数值模拟分析[J].铁道标准设计,2017,61(11):121-127,7.

铁道标准设计

OA北大核心

1004-2954

访问量0
|
下载量0
段落导航相关论文