三峡大学学报(自然科学版)2018,Vol.40Issue(1):54-58,5.DOI:10.13393/j.cnki.issn.1672-948X.2018.01.012
超大直径钻孔灌注桩成桩过程的钢护筒受力分析
Mechanical Analysis of Steel Casing Pipes of Large Diameter Cast-in-situ Bored Pile's Pile-forming Process
摘要
Abstract
Large span transmission tower built in rivers and lakes in the deepwater usually use large diameter bored pile foundation;steel casing pipes are important components which ensure the quality and safety of pouring piles into the hole and into the piles.Combining one of Su-Tong Yangtze River large span transmission tower design-large diameter cast-in-situ bored pile construction,the finite element analysis software ABAQUS is used to carry out the numerical simulation analysis of the process of large diameter cast-in-situ bored piles into piles,and study the mechanical behavior of steel casing pipes of large diameter cast-in-situ bored pile's bored and pile process in the river.Study results show that:Steel casing pipes' stress increases with the drilling process and decreases with the concrete condensation and hardening after pouring concrete.The most unfavorable conditions of pile construction process is pre-pouring concrete stage after the completion of the drilling phase;steel casing pipes' stress reaches a maximum in this condition.This condition is recommended as a control condition for steel casing pipes structure design.The maximum stress of construction after steel protecting tube pile is 24.7% of the steel strength design value.This article suggests that if structural design using steel casing pipes in pile body stress solution,the construction stress should be considered.关键词
钢护筒/ABAQUS/泥浆护壁/钻孔桩/受力性能Key words
steel casing pipes/ABAQUS/slurry-supported/bored pile/mechanical performance分类
建筑与水利引用本文复制引用
李媛媛,俞瑾,曹平周..超大直径钻孔灌注桩成桩过程的钢护筒受力分析[J].三峡大学学报(自然科学版),2018,40(1):54-58,5.基金项目
国家自然科学基金“钢—混凝土组合结构粘结滑移统一理论及其破坏准则的研究”(50478044) (50478044)