净水技术2017,Vol.36Issue(11):87-95,9.DOI:10.15890/j.cnki.jsjs.2017.11.016
黄浦江上游水源地原水系统通水切换方案
Scheme of Launch and Switchover of Raw Water Diversion System for Upstream Huangpu River Water Source
摘要
Abstract
With the purpose of getting prepared for system commissioning and raw water source switchover after completion of construction of upstream Huangpu River water source system,operation plans on pipeline water filling,system capability test,pipeline flush and raw water source switchover are proposed.According to the joint-action mechanism of Jinze and Songpu water source,different operation plans for each water source are also proposed,with hydraulic calculation based on current raw water flow rate of 5 districts benefiting from upstream Huangpu River raw water.Pressure control point and operation condition of each plan propose useful guidance of the operation of Jinze,Songjiang and Songpu pumping stations.关键词
黄浦江上游水源地/通水调试/水源切换/双水源联动/原水调度Key words
upstream Huangpu River water source/launch commissioning/raw water sources switchover/dual water sources coordination/raw water supply controlling分类
建筑与水利引用本文复制引用
李国平..黄浦江上游水源地原水系统通水切换方案[J].净水技术,2017,36(11):87-95,9.基金项目
国家“十三五”水体污染控制与治理科技重大专项(2017ZX07207003-02) (2017ZX07207003-02)