AP/CAP第三代先进核电站的反应堆厂房采用开顶式施工方式,这种方式有利于缩短土建与安装周期,但也使反应堆厂房更容易遭受恶劣气候影响.三门和海阳两个AP1000核电项目通过使用“临时屋面”提升了反应堆厂房建设期间抵御恶劣气候影响的能力,但仍有不足.本文详细研究了AP/CAP核电站的工程环境和建造逻辑,结合工程经验反馈,梳理了AP/CAP核电站临时顶盖的设计要求,研发了一种针对AP/CAP工程特点的屋面结构支座体系,并在此基础上研究了多种可满足工程…查看全部>>
The reactor building of AP/CAP nuclear power plant is constructed by an open-roof method.The open-roof method can reduce construction time,but will also make the reactor building easily affected by bad weather.Two self-reliance projects,Sanmen and Haiyang,use temporary roofs to help the reactor buildings withstand bad weather.However,the effects of using the temporary roofs were limited.Based on the construction logic,construction method and lessons learned,…查看全部>>