| 注册
首页|期刊导航|水利水电技术|黄金峡水利枢纽高水头过鱼建筑物设计

黄金峡水利枢纽高水头过鱼建筑物设计

张鹏利 朱世洪 万继伟 黎贤访

水利水电技术2017,Vol.48Issue(8):44-48,5.
水利水电技术2017,Vol.48Issue(8):44-48,5.DOI:10.13928/j.cnki.wrahe.2017.08.009

黄金峡水利枢纽高水头过鱼建筑物设计

Design of high-head fish-pass structure for Huangjinxia Water Control Project

张鹏利 1朱世洪 2万继伟 1黎贤访2

作者信息

  • 1. 陕西省引汉济渭工程建设有限公司,陕西西安,710010
  • 2. 长江勘测规划设计研究院,湖北武汉,430010
  • 折叠

摘要

Abstract

The fish-way of Huangjinxia Water Control Project belongs to a high-head fish-pass structure with the maximum operation water head of 45.5 m and the fluctuation amplitude of the upstream water level up to 10 m.In accordance with the species,behaviors and swimming abilities of the object fish,the U type trough fish-way with the clapboard of vertical joints on the same side is selected for the fish-pass structure,and then the structural dimension of the chamber of the fish-way is obtained through the relevant hydraulic calculation.For adapting to the fluctuation of the upstream water level,5 fish-outlets are arranged for the fish-way.In order to analyze the reasonability of the layout scheme for the fish-way,the integrated models of the fish-way inlet and the fish collection system as well as the partial model of the fish-way are built up,thus the velocity distribution of the surrounding area of the fish-way inlet,the hydraulic characteristics of the fish-pass pool,etc.are obtained through the simulation.The experiment result shows that the flow field distribution in the area of the fish-way inlet is suitable for fish passing upwards to the fish-way inlet,while the hydraulic condition of the fish-pass pool meets the requirement of the smooth upwards passing of the object fish as well,and then the design scheme is reasonable.

关键词

黄金峡水利枢纽/鱼道设计/模型试验

Key words

Huangjinxia Water Control Project/design of fish-way/model experiment

分类

建筑与水利

引用本文复制引用

张鹏利,朱世洪,万继伟,黎贤访..黄金峡水利枢纽高水头过鱼建筑物设计[J].水利水电技术,2017,48(8):44-48,5.

水利水电技术

OA北大核心CSCDCSTPCD

1000-0860

访问量0
|