Abstract

Based on the operation characteristics of variable speed unit,the advantages of variable speed unit in the construction of pumped storage are analyzed.Through the comparison and analysis of engineering design with and without variable speed units,the impacts of variable speed unit on construction feasibility,energy index and economic index on pumped-storage power stations in China are analyzed.The results show that the variable speed unit has a positive impact on the layout and construction of pumped storage power station in China.The research results also provide decision-making basis for the construction process of variable speed unit in China.

关键词

变速机组/水头变幅/经济比较/抽水蓄能电站

Key words

variable speed unit/water headrange/economic comparison/pumped-storage power station

分类

能源科技

引用本文复制引用

王婷婷,张正平,赵杰君,王朝阳..变速机组对我国抽水蓄能规划选点的影响分析[J].水力发电,2018,44(4):60-63,4.

基金项目

国家电网公司科技项目(大型抽水蓄能灵活控制关键技术研究) (大型抽水蓄能灵活控制关键技术研究)

水力发电

OA北大核心CSTPCD

0559-9342

访问量0
|
下载量0
段落导航相关论文