露天矿原煤破碎站移设方案优化

孙鑫

露天采矿技术2019,Vol.34Issue(1):81-83,87,4.
露天采矿技术2019,Vol.34Issue(1):81-83,87,4.DOI:10.13235/j.cnki.ltcm.2019.01.020

露天矿原煤破碎站移设方案优化

Optimization of shift plan of raw coal crushing station in open-pit mine

孙鑫1

作者信息

  • 1. 中煤科工集团沈阳设计研究院,辽宁 沈阳 110015
  • 折叠

摘要

Abstract

Aiming at the existing problems of raw coal crushing station in the first and second mining area of Huolinhe Open-pit Coal Mine, according to the developing direction and the relationship of time and space of mining field and dump, the article lists three basic solution about shift position of raw coal crushing station, gets the best place to shift after technical and economic indicators comparing, adopts the method of relocation expenses compensation to calculate the reasonable shift step distance. The optimized crushing station location can reduce coal truck haul distance and hoisting height, save freight cost, achieve the interoperability in self-provided power plant and pithead power plant.

关键词

露天煤矿/原煤破碎站/移设位置/移设步距

Key words

open-pit coal mine/raw coal crushing station/shift position/shift step distance