Taking an underground excavation (roadway/tunnel)with a buried depth of over 1 000 m as the basis condition, a simulation test apparatus with compact structure and multi-function was developed on the basis of requirements of similar simulation test. The new apparatus consists of three main units, namely the model loading reaction frame, model loading device, and intelligent hydraulic control system, and it possesses some remarkable technical superiorities such as simple structure, high strength, large loading, good stability and biaxial four-side adjustable non-uniform loading. Taking 1115(5)coal mining face in Guqiao Mine as the study case, a similar simulation study on the process of gob-side entry retaining with large section in a deep mine was conducted by the test apparatus. Test results showed that a similar simulation on the process of gob-side entry retaining which was complex mining activity was well done, and the test results coincided with the field measurements. The site actual conditions were accurately reflected by the test results.

关键词

深部采矿工程/双向四面可调加载/多功能试验装置/相似模拟/沿空留巷

Key words

deep mining engineering/biaxial four-side adjustable loading/multi-functional test apparatus/similar simulation/gob-side entry retaining

分类

矿业与冶金

引用本文复制引用

杨明,华心祝,刘志国,刘钦节..深部采矿工程多功能相似模拟装置[J].煤矿安全,2019,50(5):126-129,4.

基金项目

国家重点研发计划资助项目(2017YFF0205501) (2017YFF0205501)

浙江省重点研发计划资助项目(2018C03035) (2018C03035)

煤矿安全

OA北大核心CSTPCD

1003-496X

访问量0
|
下载量0
段落导航相关论文