特厚煤层综放沿空掘巷小煤柱合理宽度研究

孙珍平

煤矿安全2019,Vol.50Issue(9):66-70,5.
煤矿安全2019,Vol.50Issue(9):66-70,5.DOI:10.13347/j.cnki.mkaq.2019.09.017

特厚煤层综放沿空掘巷小煤柱合理宽度研究

Reasonable Width of Small Pillar of Gob-side Entry Driving in Fully Mechanized Top Coal Caving Face

孙珍平1

作者信息

  • 1. 煤科集团沈阳研究院有限公司,辽宁 抚顺 113122;煤矿安全技术国家重点实验室,辽宁 抚顺,113122
  • 折叠

摘要

Abstract

To solve the difficult problem of determining the width of small coal pillar in gob-side roadway of fully-mechanized caving in extra-thick coal seam, taking 8305 fully-mechanized caving face of Tongxin Coal Mine as the research background, according to the theory of stratum movement, using the movement characteristics of stratum in triangle slip area, the distribution law of lateral support pressure before and after gob stability is analyzed, and the rock mass breakage in triangle area is obtained. The reduction of the force on the small coal pillar before and after the fracture is the fundamental reason for the decrease of lateral support pressure. At the same time, theoretical analysis and numerical simulation are used to obtain that the width of stress reduction zone is 17 m to 21 m after the goaf is stable. The maximum width of small coal pillar in gob-side roadway of fully mechanized top-coal caving in extra-thick seam is determined to be 11.5 m, and the field test is carried out by means of rock pressure observation. The results show that the deformation of roadway is small, the setting of small coal pillar is reasonable, the maximum width of small coal pillar is 11.5 m, which can meet the needs of safety production in working face, and the coal recovery rate is increased.

关键词

特厚煤层/综放工作面/沿空掘巷/小煤柱宽度/数值模拟

Key words

extra thick coal seam/fully mechanized caving face/gob-side entry driving/small pillar width/numerical modeling