考虑阶梯碳交易和最优建设时序的园区综合能源系统规划

江训谱 吕施霖 王健 张莹颖 包哲静 于淼

电测与仪表2023,Vol.60Issue(12):11-19,9.
电测与仪表2023,Vol.60Issue(12):11-19,9.DOI:10.19753/j.issn1001-1390.2023.12.002

考虑阶梯碳交易和最优建设时序的园区综合能源系统规划

Park-level integrated energy system planning considering tiered carbon trading and optimal construction timing

江训谱 1吕施霖 2王健 2张莹颖 2包哲静 3于淼3

作者信息

  • 1. 浙江大学 工程师学院,杭州 310015
  • 2. 国网浙江省电力有限公司综合服务分公司,杭州 310005
  • 3. 浙江大学电气工程学院,杭州 310027
  • 折叠

摘要

Abstract

The integrated energy system(IES)in industrial park enables the mutual complementation and coordinated op-timization of multiple energy sources,which is of great significance for energy conservation,efficiency enhancement and carbon emission reduction.In this paper,the planning model and solution approach is proposed,considering tiered carbon trading and optimal construction timing for the IES in the park,which involves multiple energy types including electricity,gas and heat.The cost calculation model for a tiered carbon trading is developed,and the'dual-carbon'constraints of car-bon peaking and carbon neutrality are incorporated to restrict the carbon emissions of the park.The optimization objective is to minimize the net present value of the total life-cycle cost,which takes into account the investment cost,operation and maintenance cost,carbon trading cost,and residual value cost.The model is solved using a mixed-integer programming to determine the investment year and capacity configuration plan of equipment in the IES of park.To demonstrate the effec-tiveness of the planning model in reducing carbon emissions and decreasing system costs,a variety of typical scenarios are established for joint comparison of several typical planning scenarios.Additionally,the impacts of carbon trading bench-mark prices,the number of construction phases and the dual carbon constraint on the planning results are explored.

关键词

园区综合能源系统/阶梯碳交易/双碳约束/最优建设时序

Key words

integrated energy system(IES)/tiered carbon trading/dual carbon constraints/optimal construction timing

分类

信息技术与安全科学

引用本文复制引用

江训谱,吕施霖,王健,张莹颖,包哲静,于淼..考虑阶梯碳交易和最优建设时序的园区综合能源系统规划[J].电测与仪表,2023,60(12):11-19,9.

基金项目

国家电网有限公司科技项目(5211FW220001) (5211FW220001)

电测与仪表

OA北大核心CSTPCD

1001-1390

访问量0
|
下载量0
段落导航相关论文