山东建筑大学学报2023,Vol.38Issue(6):104-111,8.DOI:10.12077/sdjz.2023.06.014
海底隧道涌水量解析及工法过渡段优化研究
Analysis of water inflow and optimization of engineering transition section in undersea tunnel
摘要
Abstract
The undersea tunnel is located in a state of high confining pressure and high water pressure,and there is unlimited water supply above it.Seepage and water inrush are easy to occur during the construction process.Therefore,adjusting the corresponding construction plan based on the prediction results of water inrush can reduce the probability of water inrush.Based on the Shantou Bay Undersea Tunnel project,this paper compares the results of water inflow in various tunnels from the analytic formula and gives the most applicable prediction formula for the project.At the same time,the results are used to carry out orthogonal test,and the three factors affecting the stability of the transition section are analyzed,the order of every factors affecting the two indexes of differences of crown settlement and water inflow is determined.The results show that the result from the Macastor Analytic Formula is more safe and close to the engineering survey data.It is also found that the total length of the engineering transition section has a significant influence on the stability of the interface of surrounding rock,but the influence of excavation method and excavation progress on it is not significant.When the length of the transition section is about 10 m,the transition section has a good effect on improving the stability of the interface of surrounding rock.When the length of the transition section is greater than 10 m,the improvement effect is not significant.关键词
涌水量/关联解析式/海底隧道/工法转换Key words
water inflow/relational analytic formula/undersea tunnel/engineering transition分类
交通工程引用本文复制引用
陈云娟,王乐宁,刘丞,潘传琼..海底隧道涌水量解析及工法过渡段优化研究[J].山东建筑大学学报,2023,38(6):104-111,8.基金项目
国家自然科学基金面上项目(42172310,51609130) (42172310,51609130)
山东省青创科技团队项目(2019KJG015) (2019KJG015)
山东省矿山灾害预防控制省部共建国家重点实验室开放基金项目(MDPC0909) (MDPC0909)
山东建筑大学博士科研基金项目(XNBS1704) (XNBS1704)