江苏水利Issue(12):39-43,5.
南水北调东线工程江苏段大型泵站非电量保护研究与应用
Esearch and application on non-electricity protection of large pumping station in Jiangsu section of the eastern route of south-to-north water diversion project
沈昌荣 1杜鹏程1
作者信息
- 1. 南水北调东线江苏水源有限责任公司淮安分公司,江苏淮安 223001
- 折叠
摘要
Abstract
Aiming at the problem that a large amount of non-electrical data in pumping station equipment has not been effectively used and protected,combined with the software and hardware transformation of the monitoring system at Hongze station in Jiangsu section of the eastern route of south-to-north water diversion project,non-electrical data processing,model construction,logic perfection,fixed value management and other aspects of non-electricity protection research and pilot application are carried out to provide reference for the research of non-electricity protection of pumping station.关键词
南水北调东线工程江苏段/泵站/非电量保护Key words
Jiangsu section of the eastern route of south-to-north water diversion project/pumping station/non-electricity protection分类
建筑与水利引用本文复制引用
沈昌荣,杜鹏程..南水北调东线工程江苏段大型泵站非电量保护研究与应用[J].江苏水利,2023,(12):39-43,5.