铸造2023,Vol.72Issue(12):1649-1652,4.
五包合浇生产122t葛洲坝转轮体铸件
Production 122 Tons of Gezhouba Runner Hub Casting by 5 Ladles Combined Pouring
杨程坤 1叶文辉 2吴仁贵 2杨茂一1
作者信息
- 1. 辽宁福鞍重工股份有限公司,辽宁鞍山 114016
- 2. 中国铸造协会,北京 100084
- 折叠
摘要
Abstract
Based on the structural characteristics of runner hub used for Gezhouba hydropower station,the capacity of smelting equipment and the lifting capacity of crane,the pouring process of 5 ladles combined pouring and then 2 ladles pouring in the riser was practiced and cutting the riser in the pit at 880-900℃are formulated in this paper.The parameters of tapping,re-heating and pouring for each ladle was determined via the pouring process with 5 empty ladles,then the runner hub with net weight of 122 tons was successfully poured.Cutting riser in the pit and the annealing process was performed to make up for the shortage of crane capacity and ensure the smooth production of castings.关键词
5包合浇/转轮体/冒口补浇/ZG20MnSiKey words
5 ladles pouring/runner hub/riser teeming/ZG20MnSi分类
矿业与冶金引用本文复制引用
杨程坤,叶文辉,吴仁贵,杨茂一..五包合浇生产122t葛洲坝转轮体铸件[J].铸造,2023,72(12):1649-1652,4.