Abstract
There are four problems in the analysis of the current situation of jialu River channel and sluice project.First,the flood control standard of river channel is low.It is unable to meet the flood control standards determined by basin planning.Second,the river drainage capacity is seriously insufficient.Third,there are many hidden dangers in the project.The existing embankment is not continuous.Moreover,the flood capacity of the blocking building is insufficient.And the water obstruction is serious.The project is aging and disrepair.The problem of disease risk is prominent.Fourth,most of the branches of the estuary lack of control engineering.The backflow is serious.关键词
河道/建筑物/状况/存在问题Key words
river channel/buildings/condition/existing problems分类
建筑与水利引用本文复制引用