| 注册
首页|期刊导航|水力发电|调节性水电容量补偿方案设计研究

调节性水电容量补偿方案设计研究

张天遥 陶湘明 毛玉鑫 胡杨 周佳 黄炜斌

水力发电2024,Vol.50Issue(1):58-61,4.
水力发电2024,Vol.50Issue(1):58-61,4.

调节性水电容量补偿方案设计研究

Study of Compensation Scheme Design for Regulated Hydropower Capacity

张天遥 1陶湘明 2毛玉鑫 3胡杨 3周佳 2黄炜斌1

作者信息

  • 1. 四川大学水利水电学院, 四川 成都 610065
  • 2. 中国电建集团成都勘测设计研究院有限公司, 四川 成都 610072
  • 3. 中国长江电力股份有限公司, 湖北 宜昌 443000
  • 折叠

摘要

Abstract

To alleviate the disadvantageous position of regulated hydropower in the power market under the unitary tariff policy there is an urgent need to configure a reasonable capacity compensation mechanism.Taking the regulating hydropower as object and combining the actual power system in China a set of hydro power capacity compensation mechanism that is both practical and operable is established by using the uncompensated cost under the fixed capacity price mechanism as the evaluation method of capacity compensation pricing and six newly invested regulating hydropower stations in Yangtze River basin are taken as case example to verify the implementation effect of the scheme.The results show that the compensation scheme has clear meaning strong adaptability and reasonable calculation results.

关键词

调节性水电/容量补偿/补偿机制/市场化/两部制电价/长江流域

Key words

regulating hydropower/capacity compensation/compensation mechanism/marketization/two-part electricity price/Yangtze River basin

分类

建筑与水利

引用本文复制引用

张天遥,陶湘明,毛玉鑫,胡杨,周佳,黄炜斌..调节性水电容量补偿方案设计研究[J].水力发电,2024,50(1):58-61,4.

基金项目

国家重点研发计划(YFB0905204) (YFB0905204)