滇中引水软岩隧洞施工支洞交岔口开挖控制技术

殷本林

四川水力发电2023,Vol.42Issue(6):16-19,24,5.
四川水力发电2023,Vol.42Issue(6):16-19,24,5.

滇中引水软岩隧洞施工支洞交岔口开挖控制技术

Excavation Control Technology for Intersections of Construction Adits in Soft Rock Headrace Tunnel in the Central Yunnan

殷本林1

作者信息

  • 1. 中国水利水电第七工程局有限公司,四川成都 611730
  • 折叠

摘要

Abstract

The Shizishan Tunnel in the Dali section of the Central Yunnan Water Diversion Project is located in the red bed soft rock section with prominent deformation.In order to facilitate the construction of an ultra-long water conveyance tunnel,an inclined shaft has been set up as a construction adit.The structural span at the intersection of the adit and the main tunnel is large,making it difficult to control deformation and stability during excavation and support.This article explains deformation control measures taken based on the specific conditions,such as zoning and blocking,excavation procedures,and supporting structures at the intersection of the adit and the main tunnel,which can provide reference for the construction of similar projects.

关键词

滇中引水工程/软岩隧洞/交岔口/开挖控制技术

Key words

Central Yunnan Water Diversion Project/Soft rock tunnel/Intersection/Excavation control technol-ogy

分类

水利科学

引用本文复制引用

殷本林..滇中引水软岩隧洞施工支洞交岔口开挖控制技术[J].四川水力发电,2023,42(6):16-19,24,5.