白格堰塞湖影响下叶巴滩水电站施工导流动态规划研究
Study on the Dynamic Planning of Construction Diversion of Yebatan Hydropower Station under the Influence of Baigeyansai Lake
彭峥 1孔科 1周顺文 1张有山1
作者信息
- 1. 中国电建集团成都勘测设计研究院有限公司,四川成都 610072
- 折叠
摘要
Abstract
This paper makes a study on the dynamic planning of construction diversion of Yebatan Hydropower Station under the influence of Baigeyansai lake event.The adjusted initial diversion program and a multistage cofferdam scheme have ensured the dam excavation to be started as early as possible,reducing diversion risk and recovering project losses.The earth-rock main cofferdam is recommended after a a comprehensive eco-nomic and technical comparison,reducing investment and ensuring the smooth construction of main project.关键词
白格堰塞湖/叶巴滩水电站/导流程序/分期围堰/动态规划Key words
Baigeyansai Lake/Yebatan Hydropower Station/Diversion procedure/Multistage cofferdam/Dy-namic planning分类