| 注册
首页|期刊导航|广东水利水电|珠江三角洲水资源配置工程预应力复合衬砌足尺模型试验关键施工工艺研究

珠江三角洲水资源配置工程预应力复合衬砌足尺模型试验关键施工工艺研究

罗晶 唐欣薇 莫键豪

广东水利水电Issue(1):39-43,5.
广东水利水电Issue(1):39-43,5.

珠江三角洲水资源配置工程预应力复合衬砌足尺模型试验关键施工工艺研究

Study on Key Construction Technology of Full-Scale Model Test of Prestressed Composite Lining for Water Resources Allocation Project in the Pearl River Delta

罗晶 1唐欣薇 2莫键豪2

作者信息

  • 1. 广东水电二局股份有限公司,广州 511300
  • 2. 华南理工大学土木与交通学院,广州 510640
  • 折叠

摘要

Abstract

Based on the full-scale model test of prestressed composite lining for water resource allocation project in the Pearl River Delta,the construction technology research was carried out in terms of trolley development,inner lining concrete preparation and casting,prestressing implementation and other aspects to address the construction difficulties of this type of lining structure.Firstly,the construction contents of the prestressed composite lining full-scale model were summarized,and improvements were proposed to the existing trolley by combining the experience in the construction of the model;subsequently,the key construction technology of prestressed composite lining was studied,and specific mix proportion of concrete,matching vibrating system and the sequence of prestress tensioning were proposed to ensure the construction quality.The research results provide reference for the field construction process of prestressed composite lining.

关键词

预应力复合衬砌/足尺模型/施工工艺/作业台车/分级张拉

Key words

prestressed composite lining/full-scale model/construction technology/trolley/tensioning technology

分类

建筑与水利

引用本文复制引用

罗晶,唐欣薇,莫键豪..珠江三角洲水资源配置工程预应力复合衬砌足尺模型试验关键施工工艺研究[J].广东水利水电,2024,(1):39-43,5.

基金项目

广东省重点领域研发计划项目(编号:2019B111108001). (编号:2019B111108001)

广东水利水电

1008-0112

访问量0
|
下载量0
段落导航相关论文