Abstract
In order to study the applicability and progress of tunnel boring machine in urban rail projects,the advantages and disadvantages of using tunnel boring machine in urban rail transit were analyzed by consulting relevant materials and researching relevant cases.The impact of three factors:departure,excavation,and station crossing on construction progress was also analyzed.关键词
全断面隧道掘进机/城轨项目/适用性/施工进度Key words
tunnel boring machine/urban rail projects/applicability/construction progress分类
交通工程引用本文复制引用
杨守峰..全断面隧道掘进机在城轨项目中适用性及施工进度影响因素探讨[J].天津建设科技,2024,34(1):19-21,3.