红水河2024,Vol.43Issue(1):13-16,4.DOI:10.3969/j.issn.1001-408X.2024.01.003
多泥沙河流日调节电站以库代池方案研究
Study on Scheme of Replacing Desilting Basin with Reservoirs for Daily Regulating Power Stations in Sediment-Laden River
曾懿1
作者信息
- 1. 中国能源建设集团广西电力设计研究院有限公司, 广西 南宁 530007
- 折叠
摘要
Abstract
The river where a hydropower station is located in Nepal is a typical river with high sediment concentration.The power station is a peak-shaving runoff(PRoR)high-head power station,and sand prevention and sediment discharge are particularly important.The authors studied the feasibility and economy of the replacing desilting basin with reservoirs scheme,combined with the numerical analysis results of hydrological and sediment operation,adopted a more reasonable flushing and desilting design and anti erosion measures for the unit to save engineering investment.This study can provide reference for other similar engineering design.关键词
多泥沙/日调节水库/以库代池/水电站Key words
high concentration of sediment/daily regulation reservoir/replacing desilting basin with reservoirs/hydropower station分类
建筑与水利引用本文复制引用
曾懿..多泥沙河流日调节电站以库代池方案研究[J].红水河,2024,43(1):13-16,4.