多泥沙河流日调节电站以库代池方案研究

曾懿

红水河2024,Vol.43Issue(1):13-16,4.
红水河2024,Vol.43Issue(1):13-16,4.DOI:10.3969/j.issn.1001-408X.2024.01.003

多泥沙河流日调节电站以库代池方案研究

Study on Scheme of Replacing Desilting Basin with Reservoirs for Daily Regulating Power Stations in Sediment-Laden River

曾懿1

作者信息

  • 1. 中国能源建设集团广西电力设计研究院有限公司, 广西 南宁 530007
  • 折叠

摘要

Abstract

The river where a hydropower station is located in Nepal is a typical river with high sediment concentration.The power station is a peak-shaving runoff(PRoR)high-head power station,and sand prevention and sediment discharge are particularly important.The authors studied the feasibility and economy of the replacing desilting basin with reservoirs scheme,combined with the numerical analysis results of hydrological and sediment operation,adopted a more reasonable flushing and desilting design and anti erosion measures for the unit to save engineering investment.This study can provide reference for other similar engineering design.

关键词

多泥沙/日调节水库/以库代池/水电站

Key words

high concentration of sediment/daily regulation reservoir/replacing desilting basin with reservoirs/hydropower station