热力发电2024,Vol.53Issue(3):126-136,11.DOI:10.19666/j.rlfd.202308120
BEST小汽轮机带小发电机运行控制策略研究与应用
Research and application of BEST small steam turbine with small generator operation control strategy
吴青云 1杨博 1牛利涛 1陈志刚 1李华 2高玉峰 1何洋 1王海涛 1谭祥帅 1高奎 1何胜 2高景辉 1孟颖琪1
作者信息
- 1. 西安热工研究院有限公司,陕西 西安,710054
- 2. 华能秦煤瑞金发电有限责任公司,江西 赣州,341000
- 折叠
摘要
Abstract
In order to achieve the desired flexibility,high efficiency,and cost-effectiveness in the startup and operation of thermal power units,the utilization of the BEST small steam turbine with a small generator for the implementation of a double-turbine reheat system unit is crucial for enhancing the operational economy of the unit.According to the starting mode of the BEST system and unit,combined with the historical process and data of the starting and operation of the debugging and adjustment test,a characteristic analysis test of the BEST system in multi-mode startup and operation was conducted.The existing control logic was optimized,and an operation control strategy for the BEST small steam turbine with a small generator was proposed.The system addresses the issue of lacking control strategies in various aspects,such as the starting and control of the BEST system,converter start-stop control,BEST small steam turbine and converter non-disturbance switching,run back,load dumping conditions,and ensures uninterrupted operation control of the entire process of the BEST system.After optimization,the crucial parameters of the BEST system remain secure and stable during operation.The control method holds significant reference value for similar units equipped with the BEST system.关键词
双机回热系统机组/抽汽背压式汽轮机/启动及运行/控制策略Key words
double-turbine reheat unit/back pressure extraction steam turbine/startup and operation/control strategy引用本文复制引用
吴青云,杨博,牛利涛,陈志刚,李华,高玉峰,何洋,王海涛,谭祥帅,高奎,何胜,高景辉,孟颖琪..BEST小汽轮机带小发电机运行控制策略研究与应用[J].热力发电,2024,53(3):126-136,11.