摘要
Abstract
In this paper,taking SG01 section of Guangzhou New Baiyun International Airport Second Expressway South as an example,the prefabricated spliced integral strip foundation and integral support system are deeply analyzed.Practice has shown that the"prefabricated spli-cing integral strip foundation and integral support system"adopted in the temporary pier structure of the bridge in this project can meet the re-quirements of the code.The construction method is processed in advance in the back field and transported to the construction site during con-struction,so that the rapid assembly can be reused,shorten the construction period of lane occupation,ensure construction safety,and reduce the traffic clearing cost.The prefabricated splicing integrated strip foundation and integrated support system proposed in the article have good application effects and can provide reference for similar projects.关键词
整体式/预制拼接条形基础/支架体系Key words
Integral/Prefabricated spliced strip foundation/Support system分类
交通工程