冶金动力Issue(2):31-36,6.
高温超高压发电四机组系统设计优化与改进
Design Optimization and Improvement of High-Temperature and Ultrahigh-Pressure Four-Unit Power Generation System
王怀军 1王伟明 1张俊 1王高丰 1杜建太 2唐家毅2
作者信息
- 1. 河南安钢周口钢铁有限责任公司,河南周口 466000
- 2. 重庆赛迪热工环保工程技术有限公司,重庆 401120
- 折叠
摘要
Abstract
With the popularization and application of clean heat recovery coke ovens,the in-stalled scale of coke ovens continues to become larger,and the flue gas waste heat resources become more and more abundant and urgent to recover.Aiming at the problems of small capacity,high quan-tity,low parameters and low power generation efficiency of waste heat boilers,the first high-temperature and ultra-high-pressure with common header four-unit power generation project for clean-type heat-recovery coke oven was designed and implemented in China.This article discusses the optimized layout of the general plan,the determination of the process system scheme,the opti-mized design of the four major pipelines and the circulating cooling water system,the development and implementation of the installation and commissioning and pipe blowing scheme,and elaborates the problems of the commissioning and implementation process.Practice has proved that this type of high-temperature and ultra-high-voltage four-unit power generation system belongs to high-efficiency and energy-saving power generation technology,which is worthy of wide popularization and application.关键词
清洁型热回收焦炉/高温超高压/母管制/余热发电/设计优化Key words
clean heat recovery coke oven/high temperature and ultra-high pressure/common header/waste heat power generation/design optimization分类
信息技术与安全科学引用本文复制引用
王怀军,王伟明,张俊,王高丰,杜建太,唐家毅..高温超高压发电四机组系统设计优化与改进[J].冶金动力,2024,(2):31-36,6.