| 注册
首页|期刊导航|中南大学学报(自然科学版)|受损PPC斜拉桥主梁灌缝加固后疲劳性能试验研究

受损PPC斜拉桥主梁灌缝加固后疲劳性能试验研究

袁晟 颜东煌 王文熙 刘昀 潘权 袁明

中南大学学报(自然科学版)2024,Vol.55Issue(3):1068-1081,14.
中南大学学报(自然科学版)2024,Vol.55Issue(3):1068-1081,14.DOI:10.11817/j.issn.1672-7207.2024.03.020

受损PPC斜拉桥主梁灌缝加固后疲劳性能试验研究

Experimental study on fatigue performance of damaged PPC cable-stayed bridge main beam after crack grouting reinforcement

袁晟 1颜东煌 2王文熙 3刘昀 4潘权 2袁明2

作者信息

  • 1. 长沙理工大学土木工程学院,湖南长沙,410114||长沙理工检测咨询有限责任公司,湖南长沙,410076
  • 2. 长沙理工大学土木工程学院,湖南长沙,410114
  • 3. 湖南大学土木工程学院,湖南长沙,410082
  • 4. 湖南交通职业技术学院路桥工程学院,湖南长沙,410132
  • 折叠

摘要

Abstract

In order to further investigate the fatigue performance of the main beam of the damaged partially prestressed concrete(PPC)cable-stayed bridge after crack grouting reinforcement,a scaled model of the PPC cable-stayed bridge section with significant fatigue and static damage to the main beam for crack grouting reinforcement was used,and fatigue and post fatigue static load tests were carried out.The results show that under fatigue load,the grouting cracks do not crack again,and the stiffness of the structural system decreases rapidly in the initial stage of fatigue loading(within about 200 000 times),and gradually in the later stage.After 2.5 million times of fatigue loading,the structural system stiffness of the main beam at L/4,L/2,and 3L/4 sections decreases by 12.83%,9.48%,and 13.62%,respectively,which is larger than that of the original main beam under the fourth round of fatigue loading.However,at the end of fatigue loading,the stiffness of the structural system is still greater than the initial structural system stiffness of the original main beam under the fourth round fatigue loading.The crack grouting treatment can effectively restore the crack resistance strength and structural system stiffness of the main beam of PPC cable-stayed bridge.With the increase of load,the grouting cracks gradually open,but the position of the maximum crack width shifts.At the same time,new cracks are constantly generated,and the range of crack distribution area increases.The effect of epoxy resin adhesive greatly delays the development of crack width and improves the crack resistance of the main beam.Epoxy resin adhesive can not only repair the crack interface of concrete,but also effectively recover the bond slip damage between steel bars and concrete.The main beam of the severely damaged PPC cable-stayed bridge still has strong fatigue resistance after crack grouting treatment,and the crack resistance and stiffness of the main beam after fatigue are greatly restored.

关键词

桥梁工程/混凝土斜拉桥/部分预应力/灌缝加固/疲劳性能/模型试验

Key words

bridge engineering/concrete cable-stayed bridge/partial prestress/grouting reinforcement/fatigue performance/model test

分类

交通工程

引用本文复制引用

袁晟,颜东煌,王文熙,刘昀,潘权,袁明..受损PPC斜拉桥主梁灌缝加固后疲劳性能试验研究[J].中南大学学报(自然科学版),2024,55(3):1068-1081,14.

基金项目

国家自然科学基金资助项目(51878073,52078054,52278141) (51878073,52078054,52278141)

湖南省交通科技项目(201932) (201932)

湖南省自然科学基金资助项目(2021jj30730) (2021jj30730)

湖南省研究生科研创新项目(CX20200832)(Projects(51878073,52078054,52278141)supported by the National Natural Science Foundation of China (CX20200832)

Project(201932)supported by the Transportation Science and Technology Program of Hunan Province (201932)

Project(2021jj30730)supported by the Natural Science Foundation of Hunan Province (2021jj30730)

Project(CX20200832)supported by the Graduate Research and Innovation Program of Hunan Province) (CX20200832)

中南大学学报(自然科学版)

OA北大核心CSTPCD

1672-7207