港口航道与近海工程2024,Vol.61Issue(2):95-99,5.DOI:10.16403/j.cnki.ggjs20240220
海上栈桥预制空心板安装方案探讨
Study on Installation Plan of Prefabricated Hollow Slabs for Offshore Trestle
董行1
作者信息
- 1. 中交第二航务工程勘察设计院有限公司,湖北武汉 430060
- 折叠
摘要
Abstract
In order to effectively improve the construction technology of hollow slab girder of trestle,a seaport trestle in Meizhou Bay,Fujian Province is selected to analyze the construction technology and method of hollow slab girder from the aspects of construction preparation,hoisting and transport of hollow slabs,erection and demolition of bridge erecting machine,including the selected slings.The application of BIM safety and quality systematic platform effectively lowers the frequency of re-hoisting and deviation correction of hollow slabs during installation,accelerates the construction progress,reduces the construction cost,which serves as a reference for the installation of trestle's hollow slabs.关键词
空心板/安装/栈桥/海港Key words
hollow slab/installation/trestle/seaport分类
交通工程引用本文复制引用
董行..海上栈桥预制空心板安装方案探讨[J].港口航道与近海工程,2024,61(2):95-99,5.