Abstract
Based on the PSASP simulation platform,this paper constructs a 2025 power grid model containing Jinshang-Hubei(i.e.,the transmission line from Jinsha River upstream hydropower unit group to Hubei province)UHVDC,and then analyzes the influence of the Jinshang UHVDC access on short-circuit current,tidal current diversion and transient stability of Hubei power grid.On this basis is puts forward the corresponding stable operation control suggestions.The results of the study have a certain guiding role for Hubei power grid planning and operation.关键词
特高压直流/短路电流/潮流/暂态稳定/潮流疏散/新能源消纳Key words
UHVDC/short-circuit current/tidal current/transient stability/tidal current diversion/new energy consumption分类
信息技术与安全科学引用本文复制引用