四川水力发电2024,Vol.43Issue(2):42-46,51,6.
基于不同规范对大跨度连续刚构渡槽进行的验算对比分析
Comparative Analysis of Checking Calculation of Different Specifications for Large-span Continuous Rigid Frame Aqueducts
石瑶 1高立宝 1陈强 1代富 1王广巍1
作者信息
- 1. 中国电建集团成都勘测设计研究院有限公司,四川 成都 611130
- 折叠
摘要
Abstract
In view of the advantages of prestressed concrete(PC)continuous rigid frame aqueducts,such as su-perior mechanical performance,large span,and high bearing capacity,the(67+120+67)m continuous rigid frame aqueduct was laid out at the section of the Bid Ⅲ Sujiamiao Aqueduct of the Tingzikou Irrigation Area across the Zhangnan Expressway.This paper follows the specifications for the highway specifications and the hydraulic specifications to carry out the longitudinal checking calculation of the superstructure,and analyzes the checking results from the two aspects of the bearing capacity limit state and the normal service limit state re-spectively.The analysis results are as follows:the highway specifications are stricter than the hydraulic specifi-cations through checking calculation of the ultimate state of bearing capacity,while for the normal use limit state check,the hydraulic specifications are stricter than the highway specifications.Therefore,it is concluded that in the design of hydraulic structures such as continuous rigid frame aqueduct,it is necessary to comply with both the hydraulic specifications and the highway specifications requirements,and more importantly,it must first meet the hydraulic specifications,and then supplement according to the highway specifications.关键词
亭子口灌区/连续刚构渡槽/水工规范/公路规范/承载力极限状态/正常使用极限状态Key words
Tingzikou Irrigation Area/Continuous rigid frame aqueduct/Hydraulic specifications/Highway specifications/Ultimate state of bearing capacity/Normal use limit state分类
建筑与水利引用本文复制引用
石瑶,高立宝,陈强,代富,王广巍..基于不同规范对大跨度连续刚构渡槽进行的验算对比分析[J].四川水力发电,2024,43(2):42-46,51,6.