装配式电力综合管廊主体结构及关键节点设计和施工

伍丹 郑智洪 欧长红

市政技术2024,Vol.42Issue(5):228-232,5.
市政技术2024,Vol.42Issue(5):228-232,5.DOI:10.19922/j.1009-7767.2024.05.228

装配式电力综合管廊主体结构及关键节点设计和施工

Design and Construction of Main Structure and Key Joint of Prefabricated Power Utility Tunnel

伍丹 1郑智洪 2欧长红2

作者信息

  • 1. 湖南东方红建设集团有限公司,湖南长沙 410205||湖南东方红建筑设计研究院有限公司,湖南长沙 410205
  • 2. 湖南东方红建设集团有限公司,湖南长沙 410205
  • 折叠

摘要

Abstract

The traditional fully cast-in-place utility tunnel has a large earth excavation volume,high cost,cumber-some process,low efficiency and long construction period.But the segmental prefabricated utility tunnel has high dead-weight,hightransportation costs and assembly construction costs.Therefore,the research results of prefabri-cated utility tunnel in China were analyzed to overcome the above shortcomings.According to the project character-istics,a new design and construction method is proposed.Taking the Leifeng-Yannong 220 kV power utility tunnel project in Changsha as an example,the structural splitting design of the main body of the power utility tunnel,the deepening of prefabricated components,the design of production molds and the design of key joints are elaborated in detail as well as the construction process.Finally,the application value of this type of precast power utility tunnel was proved by the comparative data of engineering completion accounting.The design suggestions are proposed for multi-warehouse power utility tunnel.

关键词

综合管廊/装配式/结构拆分/关键节点/生产模具/设计

Key words

utility tunnel/prefabricated/structural splitting/key joint/production molds/design