北京水务Issue(z1):4-9,6.DOI:10.19671/j.1673-4637.2024.S1.002
官厅水库流域"23·7"强降雨防洪调度复盘分析
Analysis of'23·7"heavy rainfall flood control operation in Guanting Reservoir basin
王欣 1王霞 1姜树君 1宋倩 1陈雷 1吴晓冬1
作者信息
- 1. 北京市官厅水库管理处 河北张家口 075441
- 折叠
摘要
Abstract
During the period from late July to early August 2023,a heavy rainfall process occurred in the Guanting Reservoir basin.As a control hub project in the upstream of the Yongding River,Guanting Res-ervoir fully intercepted the upstream flood and reduced the flood control pressure in the downstream of the Yongding River.Through in-depth review and analysis of the rainfall,water conditions,flood forecast-ing and scheduling of the"23·7"heavy rainfall in Guanting Reservoir Basin,summarize the rainstorm runoff law and flood forecasting experience,sort out the problems existing in rainfall response and flood control operation,and put forward countermeasures and suggestions to strengthen the"four pre"capacity of Guanting Reservoir.关键词
官厅水库/"23·7"强降雨/径流分析Key words
Guanting Reservoir/"23·7"heavy rainfall/runoff analysis分类
建筑与水利引用本文复制引用
王欣,王霞,姜树君,宋倩,陈雷,吴晓冬..官厅水库流域"23·7"强降雨防洪调度复盘分析[J].北京水务,2024,(z1):4-9,6.