Abstract
In order to ensure the safe operation of Wujiazi Reservoir,prevent downstream people and property from being threatened,and continue to exert the aquaculture benefits of the reservoir,the safety situation of the reservoir project was reviewed and analyzed by collecting the relevant parameters of the reservoir.The results showed that the top elevation of the lowest point on the northwest corner of the reservoir bank,which was 101.77m,was lower than the check flood level,and the elevation of the remaining part of the reservoir bank was lower than the check flood level plus the safety super high requirement.The reservoir needs to be treated with hazard removal and reinforcement engineering,It is more feasible to adopt Plan Four for reinforcement treatment based on the actual situation of the reservoir.关键词
水库/安全复核/除险加固/方案Key words
reservoir/safety review/reinforcement of risk elimination/plan分类
建筑与水利引用本文复制引用
郭铁民..五家子水库大坝安全复核及除险加固方案[J].河南水利与南水北调,2024,53(4):86-88,3.