This paper aims to reasonably select the normal storage level of reservoir,follow the terrain and geological conditions of the area where the project is located,and fully utilize water resources.It follows the basic principle of minimizing the impact of reservoir inundation and engineering investment while ensuring engineering tasks and benefits.A comprehensive technical and economic comparison is proposed for three normal storage level schemes,namely 94.50m,95.50m,and 96.50m.Based on the comprehensive engineering geological conditions,reservoir inundation treatment,hub and building layout,ecological environment,water resource utilization,and engineering economy,it is recommended that the normal storage level of Diaozhong Reservoir be 95.50m.关键词
吊钟水库/建设任务/正常蓄水位/水库淹没/经济比较Key words
Diaozhong Reservoir/construction task/normal storage level/reservoir inundation/economical comparison分类