世界有色金属Issue(6):30-33,4.
矿区整合条件下复杂开拓系统整合优化方案研究
Integrated optimization scheme of complex development system under integrated mining area conditions
摘要
Abstract
Luoba lead-zinc mine,as a multi-mining area integrated mine,has many prominent problems such as multi-pit organization production,multi-stage inclined shaft lifting and wide underground operation points,which lead to more underground supporting personnel,low efficiency and low transportation cost.By putting forward four integrated optimization schemes of development systems and making detailed technical and economic comparison,the transportation system scheme with blind shaft,skip incline and ramp as the core is finally selected to break the production status quo of each pit opening,and integrate the mine into one body for centralized lifting and transportation.It improves the transportation efficiency,reduces the number of workers,saves and improves the cost,and reduces the difficulty of management.关键词
整合矿山/多级提升/开拓系统优化Key words
integrated mine/Multi-level lifting/Development system optimization分类
矿山工程引用本文复制引用
黄富邦,王建兵,李拥军,李帅,张钦礼,尹土兵..矿区整合条件下复杂开拓系统整合优化方案研究[J].世界有色金属,2024,(6):30-33,4.基金项目
湖南省科技创新计划资助(项目编号2023RC3035),湖南省自然科学基金项目资助(项目编号2021JJ40745). (项目编号2023RC3035)