| 注册
首页|期刊导航|城市建筑|大断面盾构内部弧形件拼装和填充层质量控制要点分析

大断面盾构内部弧形件拼装和填充层质量控制要点分析

孙先祥 李磊 贾元迪

城市建筑2024,Vol.21Issue(10):209-212,4.
城市建筑2024,Vol.21Issue(10):209-212,4.DOI:10.19892/j.cnki.csjz.2024.10.49

大断面盾构内部弧形件拼装和填充层质量控制要点分析

Analysis on the Assembly Process for the Internal Arc Components of Large-Section Shield Tunneling and Key Quality Control Points for the Filling Layer

孙先祥 1李磊 1贾元迪1

作者信息

  • 1. 上海建科工程咨询有限公司
  • 折叠

摘要

Abstract

This paper briefly introduces the current status and development of the assembly process for the internal structure of large-section shield tunneling.Based on engineering cases,the assembly process for the arc components of large-section shield and the key quality control points for the filling layer are analyzed,and a filling rate calculation method is developed.The filling quality is controlled from two aspects of the expansion degree of self-compacting concrete and the filling rate to ensure the compactness and fullness of the filling.This method can be used as a reference for the application of large-section shield arc component assembly process in similar projects.

关键词

大断面盾构/弧形件/填充层/控制要点

Key words

large-section shield tunneling/arc components/filling layer/key control points

分类

交通工程

引用本文复制引用

孙先祥,李磊,贾元迪..大断面盾构内部弧形件拼装和填充层质量控制要点分析[J].城市建筑,2024,21(10):209-212,4.

基金项目

上海建科工程咨询有限公司科研创新项目(KY10000249.20220019) (KY10000249.20220019)