This paper takes the foundation pit support and dewatering project of Poly Mingyue Chunjiang B Block in Yantai as an example to introduce the design scheme of foundation pit support,the problems encountered during construction process and the treatment measures taken,elaborate some issues on design changes,quality control,safety management and project delays in the process of foundation pit support and dewatering one by one.The project was successfully completed by implementing a series of measures.关键词
基坑支护/降水/施工工艺Key words
foundation pit support/dewatering/construction technology分类
建筑与水利引用本文复制引用