科技创新与应用2024,Vol.14Issue(18):165-168,4.DOI:10.19981/j.CN23-1581/G3.2024.18.038
济南轨道交通4号线燕山立交桥东站—浆水泉路站盾构滚刀选型及保养方法
摘要
Abstract
In response to the adverse geological factors affecting the use of cutting tools in the section between Yanshan Overpass East Station and Zhushuiquan Road Station of Jinan Urban Rail Transit Line 4 Phase I Project,this paper analyzes the adverse geological factors,rock breaking working principle of shield tunneling cutters,performance requirements of cutters,design configuration and application strategies,and then proposes measures to reduce damage to shield tunneling cutters and daily maintenance methods.关键词
盾构滚刀/盾构机/轨道交通/性能需求/装配质量Key words
Shield hob/shield machine/rail transit/performance requirements/assembly quality分类
交通运输引用本文复制引用
刘万熙,邱健,于文超,卢庆亮,栾守成..济南轨道交通4号线燕山立交桥东站—浆水泉路站盾构滚刀选型及保养方法[J].科技创新与应用,2024,14(18):165-168,4.基金项目
泰山产业领军人才工程专项经费资助(股研2022-05) (股研2022-05)