| 注册
首页|期刊导航|四川水力发电|巴塘水电站全风化地层调压井开挖与支护方案研究

巴塘水电站全风化地层调压井开挖与支护方案研究

付伟

四川水力发电2024,Vol.43Issue(3):5-7,15,4.
四川水力发电2024,Vol.43Issue(3):5-7,15,4.

巴塘水电站全风化地层调压井开挖与支护方案研究

Overview of Excavation and Support Scheme for Surge Tank in Fully Weathered Stratum of Batang Toru Hydropower Plant

付伟1

作者信息

  • 1. 中国水利水电第十工程局有限公司,四川成都 610036
  • 折叠

摘要

Abstract

The surge tank of Batang Toru Hydropower Plant in Indonesia is mainly composed of completely weathered strata with poor geological conditions,and there is a high risk of support safety during the early ex-cavation stage.After comparing multiple schemes,the final scheme is to use the support method of"bored pile+crown","ring beams+anchor"and shotcrete.This article introduces the excavation and support scheme and construction method of surge tank in completely weathered formation,providing a certain reference for the construction of similar projects in the future.

关键词

调压井/全风化/开挖支护/施工方案/巴塘水电站

Key words

Surge tank/Complete weathering/Excavation and support/Construction scheme/Batang Toru Hy-dropower Plant

分类

水利科学

引用本文复制引用

付伟..巴塘水电站全风化地层调压井开挖与支护方案研究[J].四川水力发电,2024,43(3):5-7,15,4.

四川水力发电

1001-2184

访问量1
|
下载量0
段落导航相关论文