水力发电2024,Vol.50Issue(7):65-71,7.
量化短期弃电风险的小湾、漫湾水电站水光互补中长期优化调度研究
Quantifying the Short-term Power Abandonment Risk of Xiaowan and Manwan Hydropower Stations in the Medium-and Long-term Optimal Scheduling of Hydro-solar Complementation
李红刚 1王昱倩1
作者信息
- 1. 华能澜沧江水电股份有限公司集控中心,云南 昆明 650214
- 折叠
摘要
Abstract
With continuous access of photovoltaic power stations to hydropower stations in the river basin and packaged electricity delivery to grid together,the optimal scheduling of hydro-solar complementation puts forward new requirements for the scheduling of existing cascade hydropower stations in the basin.In order to solve the practical operation problem that the existing medium-and long-term optimal hydropower scheduling rules cannot effectively avoid the risk of power abandonment in short-term hydro-solar complementary joint operation,the hydro-solar complementation of Xiaowan and Manwan hydropower stations on Lancang River basin is taken as the example to study the short-term power abandonment risk.In the study,the long-term hydrological data of Xiaowan and Manwan hydropower stations are divided into incoming water frequencies for two various photovoltaic stations capacity scenarios in the near and long term,and the short-term power abandonment risk is quantified and the medium-and long-term hydro-solar complementary optimal scheduling diagram is plotted.It is concluded that the joint scheduling can effectively reduce the power abandonment risk of hydro-solar complementary operation under different incoming water conditions,especially in the normal year with abundant water.Study can provide a reference for the formulation of actual scheduling rules.关键词
中长期调度规则/水光互补调度图/短期弃电风险/通道弃电率/小湾水电站/漫湾水电站Key words
medium-and long-term scheduling rule/hydro-solar complementary scheduling diagram/short-term power abandonment risk/channel power abandonment rate/Xiaowan Hydropower Station/Manwan Hydropower Station分类
建筑与水利引用本文复制引用
李红刚,王昱倩..量化短期弃电风险的小湾、漫湾水电站水光互补中长期优化调度研究[J].水力发电,2024,50(7):65-71,7.