佛山科学技术学院学报(自然科学版)2024,Vol.42Issue(4):41-48,8.
隧道进口穿越断层破碎带洞身开挖施工分析
Analysis on excavation construction of tunnel entrance through fracture zone of fault
王艺芳1
作者信息
- 1. 中铁十八局集团第一工程有限公司,河北涿州 072750
- 折叠
摘要
Abstract
In order to discuss the excavation of tunnel entrance through fault fracture zone,the application of three-step temporary invert method in tunnel excavation through fault fracture zone was analyzed based on Lizhou Hydropower Station project.The analysis shows that the geological conditions of the hole body in the fault fracture zone are complicated,the stability of surrounding rock is relatively poor,and the probability of collapse is relatively large.The construction method of using the temporary invert method with the combination of system anchor rod,steel mesh,steel frame and wet shotcrete can not only ensure the construction efficiency,but also effectively control the collapse problem.The construction task can be completed efficiently,safely and orderly,which can provide reference for similar engineering construction.关键词
隧道进口/断层破碎带/洞身开挖/三台阶/仰拱法Key words
tunnel entrance/fault fracture zone/tunnel excavation/three steps/invert arch method分类
建筑与水利引用本文复制引用
王艺芳..隧道进口穿越断层破碎带洞身开挖施工分析[J].佛山科学技术学院学报(自然科学版),2024,42(4):41-48,8.