首页|期刊导航|市政技术|跨铁路独塔斜拉桥索塔平转施工技术与监测研究

跨铁路独塔斜拉桥索塔平转施工技术与监测研究

郝磊磊 刘书宏 余雪平 褚少康 程高

市政技术2024,Vol.42Issue(7):161-166,174,7.
市政技术2024,Vol.42Issue(7):161-166,174,7.DOI:10.19922/j.1009-7767.2024.07.161

跨铁路独塔斜拉桥索塔平转施工技术与监测研究

Research of Horizontal Rotation Construction Technology and Monitoring of Single-tower Cable-stayed Bridge Tower across Railway

郝磊磊 1刘书宏 2余雪平 3褚少康 4程高2

作者信息

  • 1. 中铁十七局集团第二工程有限公司,陕西西安 710005
  • 2. 长安大学公路学院,陕西西安 710064
  • 3. 东莞市建设工程检测中心有限公司,广东东莞 523819
  • 4. 西安长安大学工程设计研究院有限公司陕西西安 710064
  • 折叠

摘要

Abstract

A cable-stayed railway bridge has pylons of 85 m,inward inclination of 81.22 ° for the left and right piers.The construction method employed is the combination of formwork construction with planar rotation,which has a counterclockwise rotation of 93 ° and the rotation weight of approximately 18 500 tons.In order to address safety concerns the horizontal rotation during construction because of large weight and high gravity of the pylon,a technical analysis and on-site testing were conducted to obtain the key technical points of weighing,counter weighting,attitude monitoring and adjustment.The main conclusions include:that balancing symmetric counter-weights of 50 tonnes along the lower crossbeams and segment 0 beams can reduce the center of gravity;The rotation process is sensitive to unbalanced torque and eccentricity so that pylon weighing and counter weighting errors should be strictly controlled;Before the attitude adjustment,the counterweights are moved out and the pylon's attitude is locked by temporary supports.The verticality should keep consistent before and after rotation.

关键词

独塔斜拉桥/索塔/平面转体法/称重试验/姿态监测

Key words

single-tower cable-stayed bridge/tower/planar rotation method/weighting test/attitude monitoring

分类

交通工程

引用本文复制引用

郝磊磊,刘书宏,余雪平,褚少康,程高..跨铁路独塔斜拉桥索塔平转施工技术与监测研究[J].市政技术,2024,42(7):161-166,174,7.