The spillway of a hydropower station intersects diagonally with the downstream river channel,and the distance between the flip bucket and the right bank slope of the river channel is relatively close.Using a conventional forward flip bucket will generate small flow drop,and large flow will impact the bank,endangering the foundation of the flip bucket and the stability of the right bank slope.Based on this,this study establishes a hydraulic model with a scale of 1:35 to study a new type of flip bucket structure suitable for the oblique intersection of flood discharge cavities and river channels,and the layout of flood discharge outlets near the right bank slope.The experimental results show that the inclined nose bucket has a better effect on solving the serious problem of scouring on the right bank slope.Whether it is in the case of frequent floods or low frequency floods,the right arc wall of the inclined nose bucket flips the water flow and guides it towards the middle of the riverbed,vertically stretching it significantly.The water tongue landing point is far away from the right bank slope,which is beneficial for energy dissipation and erosion prevention in downstream rivers.This study has reference significance for the selection of nose shaped ridges with similar terrains in actual hydraulic projects.关键词
消能防冲/挑流鼻坎/模型试验/舌形鼻坎/斜鼻坎Key words
dissipation and anti-erosion/flip bucket/model experimentation/tongue-shaped spillway bucket/inclined spillway bucket分类
建筑与水利引用本文复制引用
史蝶,贺翠玲,刘少斌,李鹏峰,荆海晓..泄洪洞挑流鼻坎体型优化及下游冲刷试验[J].西北水电,2024,(3):61-66,88,7.基金项目
国家自然科学基金项目(51909211) (51909211)
陕西省自然科学基础研究计划(2019JQ-744) (2019JQ-744)
西安市科技计划项目(23GXFW0050). (23GXFW0050)