云南水力发电2024,Vol.40Issue(7):23-25,71,4.DOI:10.3969/j.issn.1006-3951.2024.07.006
兰州市北滨河西延段工程1号桥施工监控技术要点
Key Points of Construction Monitoring Technology of No.1 Bridge in Lanzhou Beibinhe West Extension Project
李文华1
作者信息
- 1. 兰州交通大学土木工程学院,甘肃 兰州 730000||兰州交通大程检测有限公司,甘肃 兰州 730000
- 折叠
摘要
Abstract
The total length of Lanzhou North Ring Road Project is about 22.5km,and the upper structure of No.1 Bridge adopts a steel truss bridge.To ensure the safety of steel truss structures during construction,based on the study of bridge construction technology schemes,this paper analyzes the key points and difficulties of construction monitoring,and provides a detailed introduction to the construction monitoring technology in the construction of No.1 truss bridge.Through on-site monitoring data,technical control of elevated bridge construction is carried out to ensure bridge construction safety.关键词
1号桥/施工方案/顶推风险/施工监控/数据分析Key words
No.1 Bridge/construction plan/push risk/construction monitoring/data analysis分类
交通工程引用本文复制引用
李文华..兰州市北滨河西延段工程1号桥施工监控技术要点[J].云南水力发电,2024,40(7):23-25,71,4.